03-047-10885-00-00 | Operator | 01-01-1900 | 1190 |
03-047-10885-00-00 | Original Permit | 01-01-1900 | 35376 |
03-047-10885-00-00 | Pressure Tests Received | 01-01-1900 | |
03-047-10885-00-00 | Date Permit Issued | 03-15-1994 | Form: 2 | Original. |
03-047-10885-00-00 | Date Commenced | 03-16-1994 | |
03-047-10885-00-00 | Log Received | 03-24-1994 | |
03-047-10885-00-00 | First Production | 06-01-1994 | |
03-047-10885-00-00 | Completion Type | 06-08-1994 | Controlled Production |
03-047-10885-00-00 | Date Completed | 06-08-1994 | Form: 3 | Initial completion in M. Hale. |
03-047-10885-00-00 | Change of Operator | 07-01-1999 | Operator changed from 1190, SEAGULL MID-SOUTH, INC. to 4032, Arkoma Holding Corporation |
03-047-10885-00-00 | Change of Operator | 09-01-2000 | Operator changed from 4032, Arkoma Holding LLC to 9375, CROSS TIMBERS OPERATING COMPANY |
03-047-10885-00-00 | Change of Operator | 06-01-2001 | Operator changed from 9375, CROSS TIMBERS OPERATING INC to 9448, XTO ENERGY INC |
03-047-10885-00-00 | 2nd Allowable Request Received | 10-13-2006 | |
03-047-10885-00-00 | 2nd Allowable Request Approved | 10-30-2006 | |
03-047-10885-00-00 | Other | 10-30-2006 | Additional Completion Permit - Casey reservoir w/XTO: Arkansas Valley Turst 1-19, PM# 20973. |
03-047-10885-00-00 | Commingle Request Received | 02-20-2007 | |
03-047-10885-00-00 | Commingle Request Approved | 03-07-2007 | |
03-047-10885-00-00 | Other | 03-07-2007 | Commingle Permit - Auth/Com Casey & M. Hale. |
03-047-10885-00-00 | Date Workover Commenced | 03-26-2007 | Form: 3 | Workover commenced. |
03-047-10885-00-00 | Date Completion Form Received at AOGC | 03-28-2007 | TRK |
03-047-10885-00-00 | Form 4 (CoC) Received | 03-28-2007 | |
03-047-10885-00-00 | Initial Date Allowed to Produce | 03-29-2007 | |
03-047-10885-00-00 | Production Ceased | 04-04-2007 | |
03-047-10885-00-00 | Completion Type | 04-05-2007 | Controlled Production |
03-047-10885-00-00 | Date Completed | 04-05-2007 | TRK |
03-047-10885-00-00 | Recompleted into New Formation | 04-05-2007 | Form: 3 | Recompletion/Workover - New Casey perfs commingled w/M. Hale. |
03-047-10885-00-00 | Tracker Finish Date | 05-03-2007 | |
03-047-10885-00-00 | First Production | 07-25-2007 | |
03-047-10885-00-00 | Other | 07-25-2007 | Date of Commencement of Com Production - NoCoP rcv'd 8/28/07. |
03-047-10885-00-00 | Production Ceased | 08-31-2013 | |
03-047-10885-00-00 | Other | 07-22-2015 | Form 33 apprv'd - Temporarily Abandoned. Status Date changed from 8/4/07. |
03-047-10885-00-00 | Date Plugging Application Submitted | 07-02-2018 | Form: 11 | Date Plugging Application Submitted |
03-047-10885-00-00 | Date Plugging Application Submitted | 07-02-2018 | TRK |
03-047-10885-00-00 | Well Status | 09-25-2018 | PA |
03-047-10885-00-00 | Wellbore Status | 09-25-2018 | Plugged and Abandoned |
03-047-10885-00-00 | Form 12 (Plugging Report) Received | 09-26-2018 | |
03-047-10885-00-00 | Deviation Type | 07-14-2024 | Vertical |
03-047-10885-00-00 | Operator | 07-14-2024 | 9448 |
03-047-10885-00-00 | Well Name | 07-14-2024 | Evans |
03-047-10885-00-00 | Well Number | 07-14-2024 | 4 |
03-047-10885-00-00 | Well Type | 07-14-2024 | GAS |
03-047-10885-00-00 | Wellbore Type | 07-14-2024 | Natural Gas - Dry |