Is spill or discharge of drilling, completion or produced fluids present:
|
|
|
If yes, did spill or discharge of drilling, completion or produced fluids occur or travel off the well pad:
|
|
(If yes, complete FIR 5) |
Compliance Summary Remarks:
|
Methanol injected production well from casing and tubing approximately 5” – 7” of storm water in the secondary containment the compressor was running during the inspection shared location with Charles Young #3-19 digital pipeline meter on location other than that a clean site.
|